Lift And Shift Migration To Aws Completed In 48 Hours
The Challenge
A logistics company faced the abrupt expiration of their on-premises data center lease. They had fewer than 7 days to migrate over 30 critical enterprise applications and 5TB of active SQL databases before losing access to their physical hardware.
The SurfingCloud Solution
Utilizing AWS Application Migration Service (MGN) and Database Migration Service (DMS), we orchestrated a continuous block-level sync from their on-prem hardware into an AWS Landing Zone, ensuring complete security compliance and exact OS replication without rewriting code.
The Impact
The entire active cutover was executed seamlessly over a weekend (48 hours), completely avoiding lease penalties and incurring zero unplanned downtime for global users.